Project started: 1 September 2004
Project will be completed: 30 August 2008
| Project Year |
Date |
Milestone / Deliverable |
| Year ONE Sep. 2004 - |
November 2004 |
Launch of Excellence Team Web-site |
| |
May 2005 |
Launch of Virtual Laboratory (pilot phase) |
| |
June 2005 |
First Review Meeting |
| |
August 2005 |
Submission of first annual report |
| Year TWO Sep. 2005 - |
November 2005 |
First Workshop |
| |
March 2006 |
Publication of 1st round of working papers / edited book |
| |
June 2006 |
Second Review Meeting |
| |
August 2006 |
Submission of second annual report |
| Year THREE Sep. 2006 - |
September 2006 |
Virtual Laboratory becomes fully operational |
| |
October 2006 |
Launch Policy Brief series |
| |
June 2007 |
Second Workshop |
| |
August 2007 |
Submission of third annual report |
| Year FOUR Sep. 2007 - |
October 2007 |
Publication of 2nd round of working papers / edited book |
| |
June 2008 |
Conference |
| |
August.2008 |
Submission of final report |
| |
End 2008 |
Completion of monograph book on the project |
|